# Task Link
1 Measure resistance between: TODO: verify measurement points
2 Connect USB and verify: 3v3, Power LED
3 Connect +12v and verify 5v
4 Write FW to processor Updating
5 Verify that the Status LED is green (first power up writes the default config)
6 Enable each output in dingoConfig. Verify that the output current values are 0
7 Measure +12V at each output pad